Newfoundland Service Alliance


Go to Flash Site.

horizontal-bar.jpg (1430 bytes)
vertical-bar.jpg (1182 bytes) Corner Brook Pulp & Paper


New Stream Header Boiler - Corner Brook, Newfoundland
  • Installation of Secondary Refiner
  • Extension to Electrical Room
  • Installation of TMP III Chip Handling
  • Installation of Refiner Foundations
  • Installation of Piping Line 4 - TMP III
  • Relocation of Steam Line - Screen Room Roof
  • Installation of Foundations and Equipment - TMP III
  • Remove Heat Recovery Tower and Install S.S. Tower
  • Modifications to A-91 Conveyor
  • Groundwood Screenroom Roof Replacement
  • Electricians Workshop
  • Installation of Scrubbers and Associated Piping - TMP III
  • No. 2 Tailings Tank

 

  • Construction of Penthouse & Mezz. at Rejects Refiner
  • Enlarge openings in Finishing Room Walls
  • Isntallation of Rejects Refiner Piping
  • Install New Agitators in No. 3 Groundwood Tank
  • Screenroom Roof Piping
  • 4th Stage Cleaner Line to Bark Plant
  • Installation of Process Exhaust System and Miscellaneous Steel
  • Installation of Crane Beams and Associated Steel Work
  • Installation of Inserts in Tailings Tank and Refined Stock Tank
  • Enclosure over D-44 Conveyor
  • Deculator Steam Line Modifications
  • Maintenance Platform for Bridge Cranes
  • Installation of Chip Moisture Density Meter
  • Removal of Tailings Tank No. 1
  • Modifications to Head Box Piping - New Refiner Screen Header
  • Chip Storage Silo
  • Repairs to Bunker C Tank No. 2
  • Caustic Storage and Handling Facilities
  • No. 1 Wet End Piping Modifications
  • Reinforce concrete Beams No.1 P.M.
  • Install Piping Spools TMP Screen Room
  • No. 4 P.M. Piping
  • Inclined Screens and Rejects Refiner Mechanical
  • Installation of Spools No. 5204-PS-005
  • Relocation of Fire Line
  • White Water Bleach Tank
  • Sulphite Tank
  • Removal and Installation of Boiler Feedwater Tanks
  • Erect Structural Steel Thune Press Penthouse
  • Bleach Tank
  • Arch. of Electrical/Personnel Facilities
  • Thune Press Penthouse/Arch. and Structural Work
  • Piping for No. 2 P.M.
  • TMP Piping
  • 16" Vacuum Line
  • TMP Piping
  • Clear Water Line for Woodroom
  • TMP Modernization - Broke Canal Overflow
  • Waterous Grinders
  • Miscellaneous Piping Work No. 2 P.M. Modernization
  • Modifications to No. 4 TMP Secondary Blowline
  • Woodroom Sump Pump and Piping Installation
  • Reseal Tubes No. 1 Boiler
  • Repairs to No. 2 Digester
  • Installation of No. 3 Barking Drum
  • Groundwood Bleach Towers - Mechanical and Electrical
  • Bleach System Piping Modifications
  • Instrument Air Piping Modifications
  • Boiler Fines Handling System
  • Installation of Piping and Burners
  • Installation of Vacumn Piping
  • Instrument Air Lines for Steam Plant
  • Instrument Air Lines TMP Heat Recovery
  • Replacement of Syphons No. 6 & 7 P.M.'s
  • Relief Line Stack Extensions
  • Penstock Millwater Tie-In