- Repairs to No. 2 Digester
- Installation of No. 3 Barking Drum
- Goundwood Bleach Towers - Mechanical and Electrical
- Bleach System Piping Modifications
- Instrument Air Piping No. 3 P.M.
- Boiler Fines Handling System
- Installation of Piping and Burners
- Installation of Vacuum Piping
- Instrument Air Lines for Steam Plant
- Instruement Air Lines TMP Heat Recovery
- Vacuum Pump Piping
|

Installation of Vaccum Piping -
Grand Falls, Newfoundland |
- Penstock Millwater Tie-In
- Relocation of Condensate and Water Lines
- Tie-In Points AES Screen Removal
- 18" Blowline Modifactions
- Relocate 3" Steam Line Top No. 4 Boiler
- No. 6 and 7 P.M. Piping Modifications
- No. 6 and 7 Dryer Conversation to 2 Stage Cascade
System
- Repairs to Dryers and Steam Heads No. 7 P.M.
|
- Replacement of Syphons No. 6 & 7 P.M.'s
- Relief Line Stack Extensions
- Fabrication of Pulp Sampler
- Equipment Installation No. 4 Drum Barker
- Control and Mixing Room Piping Light Broke Pumps
- 10" Steam Line to Warm Water Tank
- Installation of No. 1 and 2 Condensate Receiver No. 6
P.M.
- Bark Handling System
- 12 Line Mixing Room
- 6" Line TM
- 12" Steam Line from 20" Header to Hot Water
Tank
- Installation of Reboilers at Abitibi-Price Paper Mill,
Grand Falls, NF
- Installation of TMP Heat Recovery System at
Abitibi-Price Paper Mill, Grand Falls, NF
|
- No. 6 & 7 P.M. Calander Improvements
- 8" S.S. Line - Spill Sump to TMP Rejects Sump
- Relocate Flat Box Vacuum Pump Header No. 3 P.M.
- Heat Exchanger Sample Stations
- Combustion Control No. 2 Boiler
- Instrument Air Supplies
- TMP Heat Recovery - Fan Platforms
- Low Pressure Steam Lines - No. 3 P.M.
- Combustion Controls No. 4 P.M.
- Installation of S.S. Lines in Stock Tank
|

Replacement of Dearator Tank - Steam Plant,
Abitibi Price, Stephenville, Paper Mill, Newfoundland |